Developer: Blue Coast Development · Nad Al Sheba 1

Royal Manor

Royal Manor is a residential project by Blue Coast Development in Nad Al Sheba 1, Dubai, with planned handover 15.12.2018, construction 77.8% complete per the DLD registry, 36 units, 45 DLD-registered sales since 2014.

Planned handover15.12.2018DLD registry
Construction77.8%DLD registry · checked 09.09.2018
Units36DLD registry
DLD sales45 since 2014DLD registry
Median sale priceAED 7 535/m²Our calculation

Every figure carries its origin: “DLD registry” is taken from the Dubai Land Department register, “Developer supplied” is stated by the developer, “Our calculation” is computed by us from the first two. Developer prices change without notice — confirm before you commit. Methodology

Layouts and sizes

TypeUnitsTypical size, sq.ft
1 Bedroom18790–870
2 Bedroom17935–1 805
Retail11 900

Size range excludes the smallest and largest 5% of units of each type.

All units are freehold. Data from the DLD registry.

Mortgage for this project

For UAE residents the down payment starts at 20% with terms up to 25 years. Estimate your payment and purchase costs for your budget.

Calculate mortgage

Estimates only; not a bank approval.

Handover date & construction progress

77.81%
  • Construction started15.09.2016
  • Planned handover (DLD register)15.12.2018
  • Status date09.09.2018
  • Progress between DLD inspections+30.71% (26.12.2017 → 09.09.2018)
  • Escrow bankDubai Islamic Bank
  • DLD project number1855

Data from the Dubai Land Department project registry (updated 08.10.2026 09:55).

Inspection history 3
025507510022.08.201709.09.2018
Actual, per inspections

Pace: 3.64% per month. At this rate 100% falls on 13.03.2019.

The pace is calculated from the past year of inspections. It is an estimate, not a developer commitment. For reference: across 1,175 completed projects the median pace is 2.48% per month and the median build takes 40 months.

Construction progress 28
09.09.2018 77.81%
Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 1 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 2 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 3 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 4 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 5 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 6 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 7 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 8 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 9 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 10 of 11Royal Manor, Nad Al Sheba 1 construction progress — 9 September 2018, 77.81% complete, photo 11 of 11
26.12.2017 47.10%
Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 1 of 8Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 2 of 8Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 3 of 8Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 4 of 8Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 5 of 8Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 6 of 8Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 7 of 8Royal Manor, Nad Al Sheba 1 construction progress — 26 December 2017, 47.10% complete, photo 8 of 8
22.08.2017 37.29%
Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 1 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 2 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 3 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 4 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 5 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 6 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 7 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 8 of 9Royal Manor, Nad Al Sheba 1 construction progress — 22 August 2017, 37.29% complete, photo 9 of 9

Construction photos are taken by the technical inspectors of the Dubai Land Department (DLD) and remain its property. We show compressed copies; full-resolution originals are available in the Real Estate Project Status service.

Recent transactions

DateTypeSize, m²Price, AED
09.09.20251 BR73.71 150 000
09.09.20252 BR100.61 580 000
29.07.20241 BR75.0518 202
29.07.20242 BR88.3611 466
29.07.20242 BR104.9731 136
29.07.20241 BR73.4507 360
16.07.20242 BR104.9760 000
16.07.20242 BR101.9680 000
16.07.20241 BR73.7510 000
16.07.20241 BR74.9530 000
16.07.20191 BR73.7555 164
16.07.20191 BR79.1596 229
16.07.20191 BR74.9564 357
16.07.20192 BR167.91 264 942
16.07.20192 BR86.9654 699
16.07.20191 BR80.8608 812
16.07.20192 BR103.2777 742
16.07.20192 BR103.2777 742
16.07.20191 BR73.4553 205
16.07.20191 BR75.0564 733
16.07.20192 BR86.9654 774
16.07.20191 BR79.1596 229
16.07.20192 BR167.61 262 983
16.07.20191 BR80.8608 812
21.02.20192 BR88.2800 000
28.01.20192 BR164.61 110 000
25.10.20182 BR164.71 000 000
09.04.20182 BR102.81 419 840
28.03.2018Shop176.52 500 000
28.03.20181 BR73.4611 819
28.03.20182 BR128.01 068 526
28.03.20182 BR100.6819 655
26.12.20171 BR75.0518 202
26.12.20171 BR73.4507 360
26.12.20172 BR88.3611 466
26.12.20172 BR104.9731 136
21.12.20172 BR104.9750 000
21.12.20172 BR101.9661 836
21.12.20171 BR73.7500 000
21.12.20171 BR74.9520 000
14.12.20171 BR73.7396 550
14.12.20172 BR100.6541 275
12.06.20171 BR80.8751 160
05.06.20171 BR80.8751 248
05.06.20171 BR80.8751 248
30.05.20171 BR80.8751 160
17.11.20141 858.112 000 000

Dubai Land Department transaction registry, updated 07.10.2026. Explore Dubai property transactions →

Registered transactions in Royal Manor

Dubai Land Department records for this building: closed transaction prices, not asking prices or estimates. Figures are medians, so a single expensive sale does not move them.

45deals since 2014
7 535AED per m², median
2%resale, the rest bought from the developer

What buyers actually paid

TypeSize, m²Price, AEDPer m²Deals
1 bedroom75564 3577 52522
2 bedrooms103760 0007 37921

Median across all recorded deals in this building. Rows with fewer than five deals are omitted: there is nothing to average there.

How the price per square metre moved

From 2019 to 2024 — -8% on the price per square metre in this building. The district moved +107% over the same period, so the building lagged the market.

6 9442017——
7 5352019——
6 9262024——

Top to bottom: purchase price per m², year, annual rent per m², gross yield.

All figures are medians. Years with fewer than eight deals are skipped; rent is shown where there are at least twenty contracts. The yield is gross — service charges are not published in the register.

Source: Dubai Land Department transaction register. The register is updated daily; the figures here are recalculated weekly.

How much is your property in Royal Manor worth?

DLD has recorded 45 sales in this building since 2014, 1 of them resales. We compare your unit with sales of the same layout here, not with asking prices. Free, reply within 24 hours.

By submitting the form you agree to the processing of your contact details.
Royal Manor

About the project

Royal Manor is a residential building by Blue Coast Real Estate Development in Nad Al Sheba 1, also identified as Nadd Al Shibba First (Meydan). The single-building project comprises basement, ground, four residential floors and a roof level, with 36 units recorded. It is active, with a completion ratio of 77.81%.

The project and building configuration

Royal Manor is planned as one residential building on Plot 6189033 in Nadd Al Shibba First (Meydan). Its recorded configuration is B+G+4+R, comprising a basement, ground floor, four upper floors and a roof level. The project has 36 units and a total recorded area of 3,525.47. Blue Coast Real Estate Development is the developer. The project began on 15 September 2016, and its recorded completion date is 15 December 2018. Its current project status is active, with a completion ratio of 77.81%.

Apartment mix

The residential mix described for Royal Manor includes 30 one-bedroom apartments and five two-bedroom apartments. These 35 apartments are identified within the development’s unit description, while the overall project unit count is recorded as 36. Royal Manor is a single-building development rather than a multi-building scheme. Its B+G+4+R format places the residences within a building that includes a basement, ground level, four floors and a roof level. The project is located in Nad Al Sheba 1, within the wider Nad Al Sheba area and near the Meydan and Mohammed Bin Rashid City corridors.

On-site amenities

Royal Manor includes retail and a swimming pool. These amenities form part of the residential building on Plot 6189033. The building is recorded in Nad Al Shibba First (Meydan), a locality also known as Nad Al Sheba 1. The wider neighbourhood includes the Nad Al Sheba Cycle Path, with 8 km, 6 km and 4 km routes for cycling and running. The cycle path has night lighting, restrooms, changing rooms, showers and lockers. Nad Al Sheba 1 also contains community parks, sports facilities and leisure facilities within its developed local road network.

Nad Al Sheba 1 location

Royal Manor is in Nad Al Sheba 1, on the eastern edge of Mohammed Bin Rashid City near Meydan. The neighbourhood combines low- to mid-rise residential areas with leisure infrastructure and local roads connecting to central Dubai and major arterial routes. The cited road distance to Burj Khalifa and Downtown Dubai is 5.5 km, while The Dubai Mall is 5.2 km away. Business Bay is 5.3 km away and DIFC is 6.5 km away. Global Village is 9.9 km away, Dubai International Airport is 11.9 km away, and Mall of the Emirates is 11.8 km away.

Schools, recreation and transport context

Rashid and Latifa Schools are cited at a distance of 0.6 km from Nad Al Sheba 1, while the Bilingual French International School is cited at 1.0 km. The community’s Nad Al Sheba Cycle Path provides three route lengths: 4 km, 6 km and 8 km. A women-focused fitness SuperClub in the locality occupies 21,000 square feet and includes boutique studios, recovery amenities and tailored wellness programming. The nearest identified Dubai Metro Red Line station is code R26, at a cited distance of 6,042 metres from the community.

Project timeline and current status

Royal Manor has a recorded start date of 15 September 2016 and a recorded completion date of 15 December 2018. The project remains listed as active. Its completion ratio is 77.81%, based on an inspection dated 9 September 2018. The project number is 1855. Royal Manor has one building and 36 total units recorded. Blue Coast Real Estate Development is named as the developer, and the project is located in Nad Al Sheba 1. The building’s recorded form is B+G+4+R, with retail and a swimming pool included among its amenities.

The developer

Blue Coast Real Estate Development is the developer of Royal Manor. The company is associated with project number 1855, a one-building residential development in Nad Al Sheba 1. Royal Manor is recorded with 36 units and a total area of 3,525.47. The project is configured as B+G+4+R and includes retail and a swimming pool. Its recorded construction start date is 15 September 2016, and its recorded completion date is 15 December 2018. The project’s current status is active, with a completion ratio of 77.81%.

Frequent questions

Who is the developer of Royal Manor?
Blue Coast Real Estate Development is the developer of Royal Manor.
Where is Royal Manor located?
Royal Manor is located in Nad Al Sheba 1, also identified as Nadd Al Shibba First (Meydan).
How many units are in Royal Manor?
Royal Manor has 36 total units recorded across one building.
What apartment types are described at Royal Manor?
The recorded apartment mix includes 30 one-bedroom apartments and five two-bedroom apartments.
What amenities does Royal Manor include?
Royal Manor includes retail and a swimming pool.
What is the current completion status of Royal Manor?
Royal Manor is active with a recorded completion ratio of 77.81%.
When was Royal Manor scheduled to complete?
The recorded completion date is 15 December 2018. The recorded project start date is 15 September 2016.
What is near Royal Manor in Nad Al Sheba 1?
The Nad Al Sheba Cycle Path has 4 km, 6 km and 8 km routes. Burj Khalifa and Downtown Dubai are cited at 5.5 km from the community.
How can I buy an apartment in Royal Manor?
Submit an enquiry via the form on this page or message us on WhatsApp — a Continental Club Property broker (RERA 31933) will help you choose a unit and send the brochure and payment plan.

Nearby projects

Get the presentation and prices

We will send floor plans, the payment plan and available units for this project.

By submitting the form you agree to the processing of your contact details.

Project data comes from the Dubai Land Department (DLD) registry.

For AI agents and researchers

Machine-readable mirrors of this page: Markdown · JSON. They carry the same figures as this page, each with its origin labelled.

How to cite:Royal Manor — Continental Club Property, from Dubai Land Department registry and developer data, 2026-10-01, https://continentalclub.ae/project/royal-manor-nad-al-sheba-1/