High Best Tower

High Best Tower is a residential project by True Future Development in Majan, Dubai, with handover Q4 2026, construction 90.6% complete per the DLD registry, 88 units.

HandoverQ4 2026Developer supplied
Construction90.6%DLD registry · checked 19 May 2026
Units88DLD registry

Every figure carries its origin: “DLD registry” is taken from the Dubai Land Department register, “Developer supplied” is stated by the developer, “Our calculation” is computed by us from the first two. Developer prices change without notice — confirm before you commit. Methodology

Payment plan 30/70

The purchase price is split into these stages.

110%Down payment
220%During construction
370%On handover

The exact schedule is confirmed in the sale agreement for the selected unit.

Mortgage for this project

For UAE residents the down payment starts at 20% with terms up to 25 years. Estimate your payment and purchase costs for your budget.

Calculate mortgage

Estimates only; not a bank approval.

Handover date & construction progress

90.64%
  • HandoverQ4 2026
  • Status date19.05.2026
  • Progress between DLD inspections+20.42% (2026-01-28 → 2026-05-19)
  • DLD project number3493

Data from the Dubai Land Department project registry (updated 24.09.2026 09:55).

Construction progress 37
19 May 2026 90.64%
High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 1 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 2 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 3 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 4 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 5 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 6 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 7 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 8 of 9High Best Tower, Majan construction progress — 19 May 2026, 90.64% complete, photo 9 of 9

Construction photos are taken by the technical inspectors of the Dubai Land Department (DLD) and remain its property. We show compressed copies; full-resolution originals are available in the Real Estate Project Status service.

Recent transactions

DateTypeSize, m²Price, AED
18.08.20262 BR148.22 492 000
13.08.20263 BR143.32 892 000
12.08.20261 BR60.51 041 776
04.08.20262 BR118.72 363 000
04.08.20262 BR148.12 490 000
26.01.2026109.83 485 897
31.12.20251 BR73.61 310 958
12.12.20252 BR101.21 595 839
09.12.20252 BR148.21 893 801
28.11.20252 BR118.71 878 351
26.11.20252 BR133.61 860 688
06.11.20252 BR118.71 878 351
20.10.20252 BR102.61 599 606
20.10.20251 BR70.71 239 566
20.10.20252 BR133.51 897 236
29.09.20252 BR98.21 595 601
29.09.20252 BR101.31 597 406
29.09.20252 BR98.21 595 602
29.09.20252 BR98.21 616 735
19.09.20252 BR118.71 865 573

Dubai Land Department transaction registry, updated 2026-09-23. Explore Dubai property transactions →

Registered transactions in High Best Tower

Dubai Land Department records for this building: closed transaction prices, not asking prices or estimates. Figures are medians, so a single expensive sale does not move them.

80deals since 2023
15 823AED per m², median
3%resale, the rest bought from the developer
+3%over the past year

The yearly figure compares the last 12 months with the 12 before them: calendar years would not work, the current one is unfinished. The district moved +3% over the same period, so the building matched it.

What buyers actually paid

TypeSize, m²Price, AEDPer m²Deals
1 bedroom661 153 84517 48321
2 bedrooms1021 599 60515 68252

Median across all recorded deals in this building. Rows with fewer than five deals are omitted: there is nothing to average there.

Source: Dubai Land Department transaction register. The register is updated daily; the figures here are recalculated weekly.

High Best Tower

About the project

High Best Tower is a retail and residential development in Majan, within Wadi Al Safa 3 in Dubai. True Future Real Estate Development is developing the project, which comprises 88 units across two buildings. The project is active, with a recorded completion ratio of 90.64% following an inspection dated 19 May 2026 and a completion date of 1 November 2026.

Project configuration

High Best Tower is configured as a retail and residential building development with basement, ground, five upper floors and a roof level. The development comprises two buildings and 88 units in total. Its location in Majan places it within the wider DubaiLand master area and the Wadi Al Safa 3 district. The project started on 1 November 2024, and its recorded total area is 8,725.84 square metres. The building format combines residential space with retail use within the same development.

Construction progress and completion

High Best Tower is active. Its completion ratio was recorded at 90.64% on the inspection dated 19 May 2026. The scheduled completion date is 1 November 2026, matching the project end date. Construction began on 1 November 2024. These dates place the project in its later construction stage, with the recorded completion ratio exceeding nine-tenths of the development.

Project scale

The development contains 88 units across two buildings. High Best Tower has a basement, ground floor, five upper floors and a roof level. The recorded project area is 8,725.84 square metres. This configuration establishes a mid-rise retail and residential development in Majan rather than a single standalone tower format. The unit count applies to the project as a whole, across both buildings.

Majan setting

High Best Tower is located in Majan, a mixed-use community in the DubaiLand master area within Wadi Al Safa 3. Majan was planned with residential, commercial, retail and entertainment land uses. The community’s original plan envisaged a high-density collection of towers, while later planning accommodated smaller plot developments and a more incremental pattern of development. Road access is the principal transport mode for the area. Majan is not directly served by a metro station; the recorded nearest Dubai Metro Red Line station is R29, 11,422 metres away.

Road connections and nearby destinations

From Majan, Global Village is 2.6 km away by road. Downtown Dubai is 12.5 km away, while The Dubai Mall is 12.4 km away and Business Bay is 11.7 km away. Mall of the Emirates is 12.1 km away, and Dubai International Financial Centre is 13.8 km away. Dubai International Airport is 18.6 km away. Dubai Marina is 17.8 km away, Palm Jumeirah is 18.1 km away and JBR Beach is 18.6 km away. Al Maktoum International Airport is 26.8 km away, while Expo City Dubai is 22.3 km away.

The wider community

Majan forms part of DubaiLand and has developed through a phased pattern of construction. Early infrastructure works, including roads and basic services, were completed in 2007. The community contains completed, active and planned schemes, reflecting its mix of residential, commercial, retail and entertainment plots. Buildings in the local area include Safa Tower and Al Rabia Tower, which rise above the predominantly mid-rise setting. Majan’s position within DubaiLand places High Best Tower near Global Village and within road reach of central Dubai districts, retail destinations, airports and coastal leisure areas.

Developer

High Best Tower is being developed by True Future Real Estate Development. The developer is associated with the active High Best Tower project in Majan, which began construction on 1 November 2024. The development is structured as two retail and residential buildings with 88 units, a basement, ground floor, five upper floors and roof level. Its scheduled completion date is 1 November 2026.

Frequent questions

Who is the developer of High Best Tower?
High Best Tower is being developed by True Future Real Estate Development.
Where is High Best Tower located?
High Best Tower is located in Majan, within Wadi Al Safa 3 in Dubai and the wider DubaiLand master area.
What is the completion status of High Best Tower?
The project is active and had a recorded completion ratio of 90.64% following the inspection dated 19 May 2026.
When is High Best Tower expected to be completed?
The scheduled completion date is 1 November 2026.
How many units are in High Best Tower?
High Best Tower comprises 88 units across two buildings.
What is the building configuration of High Best Tower?
The project is configured as retail and residential buildings with basement, ground, five upper floors and roof level.
When did construction start at High Best Tower?
The project start date is 1 November 2024.
What is close to High Best Tower in Majan?
Global Village is 2.6 km away by road. Downtown Dubai is 12.5 km away and The Dubai Mall is 12.4 km away.
How can I buy an apartment in High Best Tower?
Submit an enquiry via the form on this page or message us on WhatsApp — a Continental Club Property broker (RERA 31933) will help you choose a unit and send the brochure and payment plan.

Nearby projects

Get the presentation and prices

We will send floor plans, the payment plan and available units for this project.

By submitting the form you agree to the processing of your contact details.

Project data comes from the Dubai Land Department (DLD) registry.

For AI agents and researchers

Machine-readable mirrors of this page: Markdown · JSON. They carry the same figures as this page, each with its origin labelled.

How to cite:High Best Tower — Continental Club Property, from Dubai Land Department registry and developer data, 2026-08-25, https://continentalclub.ae/project/high-best-tower-majan/