Planned handoverQ3 2026Developer supplied
Construction30.7%DLD registry · checked 10.12.2025

Layouts and sizes

TypeUnitsTypical size, sq.ft
1 Bedroom18786–797
2 Bedroom241 055–1 848
Other units2680–1 493

Size range excludes the smallest and largest 5% of units of each type.

All units are freehold. Data from the DLD registry.

Compare with similar projects

A broker will compare this project with 3 similar ones: prices, handover dates and payment plans.

Compare in WhatsApp

Mortgage for this project

For UAE residents the down payment starts at 20% with terms up to 25 years. Indicative monthly payment for prices from 1 120 000 AED is 4 729 AED.

Calculate mortgage

Estimates only; not a bank approval.

Handover date & construction progress

30.66%
  • Construction started27.12.2024
  • Planned handover (developer)Q3 2026
  • Status date10.12.2025
  • Escrow bankMashreq Bank
  • DLD project number4169

Data from the Dubai Land Department project registry (updated 08.11.2026 05:55).

Inspection history 1
Construction progress 33
10.12.2025 30.66%
Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 1 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 2 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 3 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 4 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 5 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 6 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 7 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 8 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 9 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 10 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 11 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 12 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 13 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 14 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 15 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 16 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 17 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 18 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 19 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 20 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 21 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 22 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 23 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 24 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 25 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 26 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 27 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 28 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 29 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 30 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 31 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 32 of 33Koyo Residence By Fuji Properties, Majan construction progress — 10 December 2025, 30.66% complete, photo 33 of 33

Construction photos are taken by the technical inspectors of the Dubai Land Department (DLD) and remain its property. We show compressed copies; full-resolution originals are available in the Real Estate Project Status service.

PDF shortlist · updated 27 October 2026

Majan: new projects and prices

30 projects · prices from DLD and developers

  1. Living Legends Phase 7 Living Legends Phase 7 Majan · Studio, 1–4 BR from AED 476,000
  2. Lazord by LAPIS Lazord by LAPIS Majan · Studio, 1–2 BR from AED 499,000
  3. Living Legends Phase 4 Living Legends Phase 4 Majan · Studio, 1–4 BR from AED 523,000

27 more in the PDF: prices, handover dates, payment plans

The PDF opens instantly. Refreshed monthly from DLD data.

Your broker for this project

Tetiana Karpenko

Tetiana Karpenko

Senior Broker · Continental Club Property · RERA ORN 31933

Answers questions about Koyo Residence By Fuji Properties: current availability, payment plan, DLD registration. English and Russian.

About the project

Koyo Residence By Fuji Properties is a 44-unit development by Fuji Properties in Majan, within DubaiLand’s Wadi Al Safa 3 area. The project is Active, with a reported construction completion ratio of 30.66% and a completion date of 15 September 2026.

The project

Koyo Residence By Fuji Properties is registered under project number 4169. It has a total project area of 4259.13 and contains 44 units. The project began on 27 December 2024 and is identified as an Active development. Its reported completion ratio is 30.66%, based on an inspection dated 10 December 2025. The project’s completion date is recorded as 15 September 2026. Fuji Properties is the developer associated with Koyo Residence By Fuji Properties.

Construction progress and completion

Koyo Residence is in the Active stage of development. Construction started on 27 December 2024, and the project had reached a 30.66% completion ratio at its recorded inspection on 10 December 2025. The stated completion date is 15 September 2026. Buyers considering the project can use these dates and the recorded progress figure to place Koyo Residence within its construction timeline. The development is registered as project number 4169 and has 44 units in total.

Project scale

The development has 44 units and a recorded total project area of 4259.13. Koyo Residence is located in Majan, a mixed-use community in the wider DubaiLand master area. The project was started on 27 December 2024 and has a completion date of 15 September 2026. Its Active status and 30.66% recorded completion ratio identify it as a project under construction rather than a completed building.

Majan and the wider setting

Koyo Residence is located in Majan, a community within Wadi Al Safa 3 and the wider DubaiLand precinct. Majan was planned as a mixed-use district with residential, commercial, retail and entertainment land uses. Its original master plan included a high-density arrangement of towers, while later planning accommodated smaller plot developments and a more incremental pattern of construction. Roads and basic services for the first phase of Majan were completed in 2007. The district includes completed, active and planned projects by different developers, reflecting continuing development across the community.

Road connections from Majan

Road travel is the primary mode of access for Majan. Global Village is 2.6 km from the community centroid, while Downtown Dubai is 12.5 km away and The Dubai Mall is 12.4 km away. Business Bay is 11.7 km away, Mall of the Emirates is 12.1 km away and DIFC is 13.8 km away. Dubai International Airport is 18.6 km away. The nearest recorded Dubai Metro Red Line station is identified as R29 and is 11,422 metres from Majan.

Development activity in the community

Majan includes developments at different stages of delivery. Aras Heights is Active with a recorded completion ratio of 90.77%, while Barari Views is Active with a recorded completion ratio of 98.86%. Aras Residence and Madison Residences are recorded as Finished, each with a 100.0% completion ratio. Jade Tower is recorded as Not Started with a 0.14% completion ratio, and Lazord by LAPIS is Active with a recorded completion ratio of 2.36%. These projects sit within the broader Majan development area.

The developer

Fuji Properties is the developer of Koyo Residence By Fuji Properties. The development is located in Majan and is registered under project number 4169. It contains 44 units across a total recorded project area of 4259.13. Construction began on 27 December 2024. The project is Active, with a 30.66% completion ratio recorded at the 10 December 2025 inspection and a stated completion date of 15 September 2026.

Frequent questions

Who is the developer of Koyo Residence?
Fuji Properties is the developer of Koyo Residence By Fuji Properties.
Where is Koyo Residence located?
Koyo Residence is located in Majan, within Wadi Al Safa 3 in the wider DubaiLand area.
What is the project number for Koyo Residence?
Koyo Residence is registered under project number 4169.
How many units are in Koyo Residence?
The project contains 44 units.
What is the construction status of Koyo Residence?
Koyo Residence is Active. Its recorded completion ratio is 30.66%.
When is Koyo Residence scheduled for completion?
The recorded completion date is 15 September 2026.
When did construction start at Koyo Residence?
Construction started on 27 December 2024.
What is near Koyo Residence in Majan?
Global Village is 2.6 km from Majan’s community centroid. Downtown Dubai is 12.5 km away and The Dubai Mall is 12.4 km away.
How can I buy an apartment in Koyo Residence By Fuji Properties?
Submit an enquiry via the form on this page or message us on WhatsApp — a Continental Club Property broker (RERA 31933) will help you choose a unit and send the brochure and payment plan.

Nearby projects

Get the presentation and prices

We will send floor plans, the payment plan and available units for this project.

By submitting the form you agree to the processing of your contact details, including for advertising analytics.

Project data comes from the Dubai Land Department (DLD) registry.

Every figure carries its origin: “DLD registry” is taken from the Dubai Land Department register, “Developer supplied” is stated by the developer, “Our calculation” is computed by us from the first two. Developer prices change without notice — confirm before you commit. Methodology

For AI agents and researchers

Machine-readable mirrors of this page: Markdown · JSON. They carry the same figures as this page, each with its origin labelled.

How to cite:Koyo Residence By Fuji Properties — Continental Club Property, from Dubai Land Department registry and developer data, 2026-10-01, https://continentalclub.ae/project/koyo-residence-by-fuji-properties-majan/

Where should we send the shortlist?

The PDF downloads right after you submit. A manager gets in touch only if you ask.