Developer: Azizi Developments · Azizi Riviera

Azizi Riviera 50

Azizi Riviera 50 is a residential project by Azizi Developments in Azizi Riviera, Dubai, with prices from AED 1 127 560, handover 13.03.2027, construction 60.9% complete per the DLD registry, 158 units, 81 DLD-registered sales since 2025.

Price fromAED 1 127 560Developer supplied
Unit typesStudio · 1 · 2 · 4 BR448–2 134 ft²DLD registry
Handover13.03.2027DLD registry
Construction60.9%DLD registry · checked 07.08.2026

Layouts and sizes

TypeUnitsTypical size, sq.ft
Studio82448–460
1 Bedroom116771–922
2 Bedroom261 202–1 322
4 Bedroom22 134
Other units8704–2 269

Size range excludes the smallest and largest 5% of units of each type.

All units are freehold. Data from the DLD registry.

Payment plan 30/70

The purchase price is split into these stages.

110%Down payment
220%During construction
370%On handover

The exact schedule is confirmed in the sale agreement for the selected unit.

Mortgage for this project

For UAE residents the down payment starts at 20% with terms up to 25 years. Indicative monthly payment for prices from 1 127 560 AED is 4 761 AED.

Calculate mortgage

Estimates only; not a bank approval.

Handover date & construction progress

60.92%
  • StatusActive
  • Construction started13.03.2025
  • Handover13.03.2027
  • Status date07.08.2026
  • Progress between DLD inspections+14.53% (19.01.2026 → 07.08.2026)
  • Escrow bankADCB
  • DLD project number3614

Data from the Dubai Land Department project registry (updated 20.10.2026 09:55).

Inspection history 4
025507510008.04.202507.08.2026
Actual, per inspections

Pace: 2.26% per month. At this rate 100% falls on 14.01.2028.

The pace is calculated from the past year of inspections. It is an estimate, not a developer commitment. For reference: across 1,175 completed projects the median pace is 2.48% per month and the median build takes 40 months.

Construction progress 46
07.08.2026 60.92%
Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 1 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 2 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 3 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 4 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 5 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 6 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 7 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 8 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 9 of 10Azizi Riviera 50, Azizi Riviera construction progress — 7 August 2026, 60.92% complete, photo 10 of 10
19.01.2026 46.39%
Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 1 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 2 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 3 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 4 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 5 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 6 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 7 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 8 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 9 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 10 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 11 of 12Azizi Riviera 50, Azizi Riviera construction progress — 19 January 2026, 46.39% complete, photo 12 of 12
18.08.2025 34.59%
Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 1 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 2 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 3 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 4 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 5 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 6 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 7 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 8 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 9 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 10 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 11 of 12Azizi Riviera 50, Azizi Riviera construction progress — 18 August 2025, 34.59% complete, photo 12 of 12
08.04.2025 28.64%
Azizi Riviera 50, Azizi Riviera construction progress — 8 April 2025, 28.64% complete, photo 1 of 2Azizi Riviera 50, Azizi Riviera construction progress — 8 April 2025, 28.64% complete, photo 2 of 2

10 more photos in the DLD register

Construction photos are taken by the technical inspectors of the Dubai Land Department (DLD) and remain its property. We show compressed copies; full-resolution originals are available in the Real Estate Project Status service.

Recent transactions

DateTypeSize, m²Price, AED
08.10.20262 BR111.72 303 380
30.09.20261 BR72.51 855 100
10.09.20262 BR111.73 104 530
10.09.2026Studio42.11 013 670
10.09.20261 BR72.51 825 390
10.09.20261 BR71.71 682 400
10.09.20261 BR72.51 821 830
09.09.2026Studio42.11 015 560
01.09.20261 BR72.51 973 700
20.08.202676.84 647 120
17.08.2026Studio41.71 133 990
04.08.202663.44 775 175
24.07.2026Studio42.1966 812
24.07.2026Studio42.1967 414
24.07.2026Studio42.1969 220
24.07.2026Studio42.1961 394
24.07.2026Studio42.1963 200
24.07.2026Studio42.1966 210
16.07.2026Studio42.71 124 550
15.07.2026Studio42.11 014 300
13.07.2026Studio42.11 000 000
13.07.20261 BR78.31 200 000
13.07.20261 BR78.31 200 000
13.07.202669.14 816 100
10.07.20262 BR111.62 830 500
08.07.20261 BR72.51 737 280
07.07.20261 BR78.32 080 460
06.07.2026Studio41.71 036 750
30.06.20262 BR111.62 798 160
29.06.20262 BR111.62 828 800
23.06.20262 BR111.62 826 900
22.06.20261 BR71.71 832 400
19.06.2026Studio42.11 044 900
18.06.20261 BR71.72 002 715
10.06.20261 BR71.71 829 100
09.06.20261 BR78.32 264 160
04.06.20261 BR72.51 789 590
02.06.2026114.010 378 720
25.05.2026Studio42.11 040 000
22.05.20261 BR71.71 566 950
22.05.20261 BR71.71 566 950
21.05.20262 BR118.72 904 850
21.05.20262 BR111.63 109 535
20.05.20261 BR78.31 742 320
19.05.20261 BR78.31 918 080
18.05.2026Studio42.1926 400
18.05.20261 BR72.51 577 730
14.05.2026Studio42.1962 500
14.05.2026Studio42.1960 960
14.05.2026Studio42.1983 550

Dubai Land Department transaction registry, updated 19.10.2026. Explore Dubai property transactions →

Registered transactions in Azizi Riviera 50

Dubai Land Department records for this building: closed transaction prices, not asking prices or estimates. Figures are medians, so a single expensive sale does not move them.

81deals since 2025
24 850AED per m², median
0%resale, the rest bought from the developer

What buyers actually paid

TypeSize, m²Price, AEDPer m²Deals
Studio421 014 30024 15030
1 bedroom721 825 39025 35332
2 bedrooms1122 826 90025 24015

Median across all recorded deals in this building. Rows with fewer than five deals are omitted: there is nothing to average there.

Source: Dubai Land Department transaction register. The register is updated daily; the figures here are recalculated weekly.

How much is your property in Azizi Riviera 50 worth?

DLD has recorded 81 sales in this building since 2025. We compare your unit with sales of the same layout here, not with asking prices. Free, reply within 24 hours.

By submitting the form you agree to the processing of your contact details, including for advertising analytics.

Amenities

  • 3.2km running and cycling track
  • Barbeque areas
  • Basketball courts
  • Tennis courts
  • Playgrounds
  • Parks
  • Les Jardins Lake
  • 2.7km swimmable lagoon
  • Swimming pool with water feature
  • Kids swimming pool
  • BBQ seating area
  • Zen garden
  • Cinema lounge

Places nearby

Azizi Riviera 50

About the project

Azizi Riviera 50 is an active residential and commercial project by Azizi Developments in the Azizi Riviera community in Meydan, Mohammed Bin Rashid City, Dubai. The building is configured as 2B+G+7+R and is planned with concrete structure, blockwork, and internal and external finishes. Construction was 60.92% complete at the inspection dated 7 August 2026, with completion scheduled for 13 March 2027.

The project

Azizi Riviera 50 forms part of Azizi Riviera in Meydan, Mohammed Bin Rashid City. The individual project is a single building with two basement levels, a ground floor, seven floors and a roof level. It combines residential and commercial uses, while the residential offering includes studios and one-, two- and three-bedroom apartments. Retail shops are also listed within the project. The planned construction comprises a concrete structure and blockwork, followed by internal and external finishes. Azizi Riviera is arranged around three community districts: the retail Boulevard, Lagoon Walk and Les Jardins. Lagoon Walk includes artisan eateries and boutiques, while Les Jardins is presented as a landscaped social space.

Apartment types and views

The apartment selection at Azizi Riviera 50 comprises studio, one-bedroom, two-bedroom and three-bedroom layouts. The project also includes retail shops. Listed outlooks include canal views towards the crystal lagoon, boulevard views, park views, swimming pool and garden views, and community views. These view categories reflect the wider Riviera setting, which brings together the Boulevard, landscaped areas and the lagoon environment. Azizi Riviera’s masterplan includes residential buildings alongside amenity spaces and a central water feature known as the crystal lagoon. The development is within the Meydan One master development in Mohammed Bin Rashid City.

Community amenities

Azizi Riviera lists a 3.2 km running and cycling track, 71 barbecue areas, basketball courts, tennis courts, playgrounds and parks. Les Jardins Lake and a 2.7 km-long swimmable lagoon are also part of the community amenities. Within the listed facilities are a swimming pool with a water feature, a kids’ swimming pool, a barbecue seating area, a Zen garden and a cinema lounge. The community’s three districts combine the retail Boulevard, Lagoon Walk and Les Jardins. Lagoon Walk is identified with artisan eateries and boutiques, while Les Jardins is a green social area. These facilities sit within the Azizi Riviera community of which Azizi Riviera 50 is a part.

Meydan and Mohammed Bin Rashid City location

Azizi Riviera 50 is located in Azizi Riviera, Meydan, Mohammed Bin Rashid City, Dubai. The project’s registered area is Al Merkadh, and Azizi Riviera sits within the Meydan One master development. Mohammed Bin Rashid City is listed as 15 minutes from Riviera. Within the local area, North London Collegiate School Dubai is 0.9 km away and Hartland International School is 1.1 km away. Both schools hold a ‘Very Good’ government inspection rating. The wider Riviera community is a waterfront residential subcommunity with landscaped courtyards and the crystal lagoon as its central water feature.

Construction progress and scheduled completion

Azizi Riviera 50 has active project status. Construction started on 13 March 2025, and the scheduled completion date is 13 March 2027. The project reached 60.92% completion at the inspection conducted on 7 August 2026. It is a one-building development. The project is designed as a 2B+G+7+R residential and commercial building, with concrete construction, blockwork and internal and external finishing works. The active status and completion figure relate specifically to Azizi Riviera 50 rather than to the wider Azizi Riviera community, where multiple buildings are arranged across different phases.

The developer

Azizi Riviera 50 is developed by Azizi Developments. Azizi Developments was founded in 2004. Azizi Riviera is a development by Azizi Developments within the Meydan One master development in Mohammed Bin Rashid City. The Riviera community includes multiple low- and mid-rise residential buildings, landscaped courtyards and the crystal lagoon. Azizi Riviera 50 adds a residential and commercial building to this setting, with studio through three-bedroom apartments and retail shops listed in its configuration. The developer’s name associated with the project is Azizi Developments L.L.C., trading as Azizi Developments.

Frequent questions

Who is the developer of Azizi Riviera 50?
Azizi Riviera 50 is developed by Azizi Developments. Azizi Developments was founded in 2004.
Where is Azizi Riviera 50 located?
Azizi Riviera 50 is in Azizi Riviera, Meydan, Mohammed Bin Rashid City, Dubai. Its registered area is Al Merkadh.
What types of apartments are available at Azizi Riviera 50?
The listed residences are studio, one-bedroom, two-bedroom and three-bedroom apartments. Retail shops are also included.
What is the building configuration of Azizi Riviera 50?
The project is configured as 2B+G+7+R. It is a residential and commercial building with two basement levels, a ground floor, seven floors and a roof level.
What amenities are listed at Azizi Riviera?
Listed amenities include a 3.2 km running and cycling track, a 2.7 km-long swimmable lagoon, parks, playgrounds, basketball and tennis courts, pools, barbecue areas, a Zen garden and a cinema lounge.
What is nearby Azizi Riviera 50?
Mohammed Bin Rashid City is listed as 15 minutes from Riviera. North London Collegiate School Dubai is 0.9 km away and Hartland International School is 1.1 km away.
What is the construction status of Azizi Riviera 50?
Azizi Riviera 50 is active and was 60.92% complete at the inspection dated 7 August 2026.
When is Azizi Riviera 50 scheduled for completion?
The scheduled completion date is 13 March 2027. Construction started on 13 March 2025.
How can I buy an apartment in Azizi Riviera 50?
Submit an enquiry via the form on this page or message us on WhatsApp — a Continental Club Property broker (RERA 31933) will help you choose a unit and send the brochure and payment plan.

Nearby projects

Get the presentation and prices

We will send floor plans, the payment plan and available units for this project.

By submitting the form you agree to the processing of your contact details, including for advertising analytics.

Project data comes from the Dubai Land Department (DLD) registry.

Every figure carries its origin: “DLD registry” is taken from the Dubai Land Department register, “Developer supplied” is stated by the developer, “Our calculation” is computed by us from the first two. Developer prices change without notice — confirm before you commit. Methodology

For AI agents and researchers

Machine-readable mirrors of this page: Markdown · JSON. They carry the same figures as this page, each with its origin labelled.

How to cite:Azizi Riviera 50 — Continental Club Property, from Dubai Land Department registry and developer data, 2026-10-17, https://continentalclub.ae/project/azizi-riviera-50-azizi-riviera/