31 Above By Beyond

31 Above By Beyond is a residential project by Beyond Developments in Maritime City, Dubai, with handover 30.12.2028, construction 0.5% complete per the DLD registry.

Construction0.5%

Construction progress

0.51%
  • Handover30.12.2028
  • Status date18.06.2026
  • DLD project number4183

Data from the Dubai Land Department project registry (updated 18.08.2026 09:55).

Construction progress 6
18 June 2026 0.51%
31 Above By Beyond, Maritime City construction progress — 18 June 2026, 0.51% complete, photo 1 of 431 Above By Beyond, Maritime City construction progress — 18 June 2026, 0.51% complete, photo 2 of 431 Above By Beyond, Maritime City construction progress — 18 June 2026, 0.51% complete, photo 3 of 431 Above By Beyond, Maritime City construction progress — 18 June 2026, 0.51% complete, photo 4 of 4

Construction photos are taken by the technical inspectors of the Dubai Land Department (DLD) and remain its property. We show compressed copies; full-resolution originals are available in the Real Estate Project Status service.

Recent transactions

DateTypeSize, m²Price, AED
18.06.2026265.311 004 480
05.06.2026231.39 630 000
20.05.2026357.912 527 640
20.05.2026231.38 934 120
20.05.2026367.413 704 320
19.05.2026386.815 345 000
19.05.2026203.38 081 280
19.05.2026265.311 004 480
05.05.2026367.414 237 760
21.04.2026312.511 936 000
08.04.2026357.913 745 000
06.04.2026273.511 180 000
26.03.2026328.212 852 550
26.03.2026261.39 778 000
26.03.2026386.815 483 000
26.03.2026386.815 483 000
26.03.2026386.815 345 000
24.03.2026386.815 414 000
24.03.2026265.311 199 000
17.03.2026350.612 722 000

Dubai Land Department transaction registry, updated 2026-08-16. Explore Dubai property transactions →

Registered transactions in 31 Above By Beyond

Dubai Land Department records for this building: closed transaction prices, not asking prices or estimates. Figures are medians, so a single expensive sale does not move them.

115deals since 2025
39 946AED per m², median
0%resale, the rest bought from the developer

Source: Dubai Land Department transaction register. The register is updated daily; the figures here are recalculated weekly.

31 Above By Beyond

About the project

31 Above By Beyond is an active 118-unit project in Dubai Maritime City, with a recorded total area of 33,745.54. It is being developed by Beyond Vespera Real Estate Development. The project was recorded at 51% completion on 18 June 2026, with a completion date of 30 December 2028.

Project overview

31 Above By Beyond is registered under project number 4183 in Dubai Maritime City. The development has 118 units and a recorded total area of 33,745.54. Its registered start date is 30 April 2026 and its recorded completion date is 30 December 2028. As of the inspection dated 18 June 2026, the project status was Active and the completion ratio was 51%. The project sits within a district developed as a maritime-focused commercial and industrial zone, with residential and mixed-use schemes also being developed in the Commercial Precinct.

Dubai Maritime City setting

Dubai Maritime City occupies a purpose-built peninsula between Port Rashid and Dubai Dry Docks. The district was launched in 2004 and developed through staged reclamation. It covers 2.3 million square metres and combines industrial, commercial and residential functions. The masterplan identifies marine services, marine management, product marketing, marine research and education, recreation, and ship design and manufacturing as its six target sectors. DP World acquired Dubai Maritime City in 2017, followed by a revised masterplan in 2019. Infrastructure development has continued across the district, including road and utility works.

District infrastructure and precincts

Dubai Maritime City is divided between an operational Industrial Precinct and a Commercial Precinct that continues to be developed in phases. The Industrial Precinct includes ship lifts, ship-repair plots, warehouses, workshops, supporting retail and showrooms. It was complete and operational, with 299 business partners and an 82% occupancy rate reported in November 2021. The Commercial Precinct is planned to include retail, residential space, offices and a promenade. More than 90% of the district’s underground utility networks, including sewerage, stormwater, water, fire, irrigation and telecom networks, have been completed.

Road access and nearby destinations

Reference driving distances from Dubai Maritime City include 6.3 km to Dubai International Financial Centre, 7.8 km to both Burj Khalifa and The Dubai Mall, 9.0 km to Business Bay, and 10.1 km to Dubai International Airport. Mall of the Emirates is 17.8 km away, Palm Jumeirah is 21.4 km away and Dubai Marina is 24.2 km away. Typical driving times are stated as 18 minutes to Dubai Mall, 20 minutes to Dubai International Airport, 30 minutes to Palm Jumeirah, 29 minutes to Burj Al Arab and 34 minutes to The Walk JBR. Al Maktoum International Airport has a typical driving time of 54 minutes.

Public transport

The nearest metro connection to the centre of Dubai Maritime City is Green Line station G24, at a distance of 2,331 m. The station is not considered walkable from the development’s centre. The project’s district location is on Dubai’s port side, close to central Dubai and within reach of Downtown Dubai, DIFC, Business Bay and Dubai International Airport by road. This position places 31 Above By Beyond in a district that combines port-related activity with an expanding commercial and residential precinct.

Development activity in the district

Dubai Maritime City includes completed and under-construction towers alongside residential and mixed-use schemes. Named developments in and around the district include The Pier Residence, Riva Residence, Oceanz, Nautica One, LIV Maritime, Harbour Lights, Franck Muller Yachting and Coral Reef. Other projects include Nautica Two and Hilton Residences Dubai Maritime City. The district’s Industrial Precinct remains dedicated to maritime operations such as ship repair and maintenance, marine logistics, ship design and manufacturing, marine-related showrooms and workshops, while the Commercial Precinct is being built out with mixed-use elements.

Frequent questions

Who is the developer of 31 Above By Beyond?
31 Above By Beyond is being developed by Beyond Vespera Real Estate Development.
Where is 31 Above By Beyond located?
The project is located in Dubai Maritime City, on a peninsula between Port Rashid and Dubai Dry Docks.
How many units are in 31 Above By Beyond?
The project has 118 units.
What is the current completion status of 31 Above By Beyond?
The project is Active and was recorded at 51% completion on 18 June 2026.
When is 31 Above By Beyond due for completion?
The recorded completion date is 30 December 2028.
What is near 31 Above By Beyond?
Dubai International Financial Centre is 6.3 km away, while Burj Khalifa and The Dubai Mall are each 7.8 km away by reference driving distance.
What is the nearest metro station to Dubai Maritime City?
Green Line station G24 is 2,331 m from the centre of Dubai Maritime City and is not considered walkable from the development’s centre.
How far is Dubai International Airport from Dubai Maritime City?
Dubai International Airport is 10.1 km away by reference driving distance, with a typical driving time of 20 minutes.
How can I buy an apartment in 31 Above By Beyond?
Submit an enquiry via the form on this page or message us on WhatsApp — a Continental Club Property broker (RERA 31933) will help you choose a unit and send the brochure and payment plan.

Nearby projects

Get the presentation and prices

We will send floor plans, the payment plan and available units for this project.

By submitting the form you agree to the processing of your contact details.

Project data comes from the Dubai Land Department (DLD) registry.