by Damac Properties in Damac Hills
Damac Hills – Golf Greens 1 is a residential project by Damac Properties in Damac Hills, Dubai, with handover 30.03.2027, construction 31.5% complete per the DLD registry.
Construction progress
- Handover30.03.2027
- Status date14.04.2026
- DLD project number2779
Data from the Dubai Land Department project registry (updated 12.08.2026 09:55).
Construction photos are taken by the technical inspectors of the Dubai Land Department (DLD) and remain its property. We show compressed copies; full-resolution originals are available in the Real Estate Project Status service.
All Dubai construction in the DLD register · Developer: Damac Properties · District: Damac Hills
Recent transactions
| Date | Type | Size, m² | Price, AED |
|---|---|---|---|
| 20.07.2026 | 2 BR | 124.9 | 2 288 730 |
| 20.07.2026 | 2 BR | 202.4 | 3 011 760 |
| 10.07.2026 | 1 BR | 62.7 | 1 040 000 |
| 06.07.2026 | 2 BR | 124.9 | 2 488 000 |
| 02.07.2026 | 2 BR | 124.9 | 1 977 000 |
| 26.06.2026 | 1 BR | 64.9 | 1 230 000 |
| 16.06.2026 | 2 BR | 212.7 | 3 197 700 |
| 15.06.2026 | 2 BR | 202.4 | 3 011 760 |
| 10.06.2026 | 1 BR | 62.7 | 900 000 |
| 22.04.2026 | 2 BR | 120.0 | 2 417 000 |
| 02.04.2026 | 2 BR | 124.9 | 2 354 000 |
| 26.03.2026 | 2 BR | 124.9 | 2 461 000 |
| 17.03.2026 | 2 BR | 124.9 | 2 259 840 |
| 09.03.2026 | 2 BR | 114.1 | 2 543 000 |
| 26.02.2026 | 2 BR | 124.9 | 2 381 000 |
| 26.02.2026 | 2 BR | 114.1 | 2 666 000 |
| 28.01.2026 | 2 BR | 127.2 | 2 665 000 |
| 12.01.2026 | 2 BR | 127.2 | 2 585 050 |
| 06.01.2026 | 1 BR | 68.9 | 1 205 000 |
| 24.12.2025 | 2 BR | 124.9 | 1 937 000 |
Dubai Land Department transaction registry, updated 2026-08-11. Explore Dubai property transactions →
Places nearby
About the project
Damac Hills – Golf Greens 1 is a three-building residential development by Damac Crescent Properties in Damac Hills, within Al Hebiah Third. The project contains 479 units and is active, with construction recorded at 31.46% completion at the inspection dated 14 April 2026. Its recorded project completion date is 30 March 2027.
Project configuration
Golf Greens 1 is planned as a residential project comprising three buildings and 479 units. The development has the project number 2779 and forms part of Damac Hills, a gated residential community in DubaiLand. Construction began on 28 December 2023. The project is listed as active, and its recorded completion ratio was 31.46% at the inspection dated 14 April 2026. The recorded end date for the project is 30 March 2027. Damac Crescent Properties is named as the developer of Golf Greens 1.
Building form and construction
The registered building configuration for Golf Greens 1 is G+3P+31+R residential. This configuration is recorded across the project’s three buildings. The construction specification describes a concrete structure and blockwork, with internal and external finishes. The scheme is therefore registered as a purpose-built residential development rather than a mixed-use or hotel project. Its 479-unit total applies to the project as a whole, across the three-building configuration.
Damac Hills setting
Golf Greens 1 is located in Damac Hills, a master-planned gated community in the DubaiLand area. Damac Hills is organised around an 18-hole championship golf course and parkland. The community includes residential clusters of villas, townhouses and apartment buildings, along with retail and leisure components. Its dedicated park area extends to 400,000 square metres. The wider community also includes golf-course villas, park villas, golf residences, park residences and The Masters villa clusters. Golf Greens 1 sits within this established masterplan while remaining a separate active residential project with its own recorded construction programme.
Community amenities
Damac Hills includes an 18-hole championship golf course developed in collaboration with Donald Trump and opened in February 2017. Community facilities include a clubhouse with restaurants, a swimming pool and a gym. Little Village is a children’s play area within the community. Supermarkets, pharmacies, banks, schools and nurseries are also included in Damac Hills, alongside retail elements centred on Damac Mall. These amenities serve the wider Damac Hills community. The golf course, parkland, retail and leisure facilities are part of the established setting for Golf Greens 1.
Connections from Damac Hills
Damac Hills is 12.7 km from Dubai Marina and Expo City Dubai, and 13.3 km from JBR Beach. Palm Jumeirah is 14.8 km away, while Mall of the Emirates is 11.4 km from the community. The Dubai Mall is 19.2 km away and Dubai International Airport is 27.6 km away. Global Village is 7.3 km from Damac Hills. The nearest cited Dubai Metro connection is the Red Line, 9.0 km from the community. Driving estimates place The Dubai Mall at 25 minutes and Dubai International Airport at 41 minutes, subject to traffic conditions.
Construction timetable
The recorded start date for Damac Hills – Golf Greens 1 is 28 December 2023. Its status is active, and the completion ratio was 31.46% at the inspection dated 14 April 2026. The project’s recorded completion date is 30 March 2027. Golf Greens 1 has 479 units across three buildings, allowing buyers to assess its construction progress and completion schedule against a defined project scale. Damac Crescent Properties is the named developer for the project.
Registered transactions in Damac Hills – Golf Greens 1
Dubai Land Department records for this building: closed transaction prices, not asking prices or estimates. Figures are medians, so a single expensive sale does not move them.
The yearly figure compares the last 12 months with the 12 before them: calendar years would not work, the current one is unfinished. The district moved +3% over the same period, so the building lagged.
What buyers actually paid
| Type | Size, m² | Price, AED | Per m² | Deals |
|---|---|---|---|---|
| 1 bedroom | 65 | 1 173 000 | 18 046 | 367 |
| 2 bedrooms | 122 | 2 066 130 | 16 935 | 120 |
Median across all recorded deals in this building. Rows with fewer than five deals are omitted: there is nothing to average there.
How the price per square metre moved
From 2023 to 2025 — +9% on the price per square metre in this building. The district moved +18% over the same period, so the building lagged the market.
Top to bottom: purchase price per m², year, annual rent per m², gross yield.
All figures are medians. Years with fewer than eight deals are skipped; rent is shown where there are at least twenty contracts. The yield is gross — service charges are not published in the register.
* 2026 is still in progress and its bar covers part of the year. The growth figure above uses completed years.
Source: Dubai Land Department transaction register. The register is updated daily; the figures here are recalculated weekly.