# Island Park I

Emaar Properties · Dubai Creek Harbour · Dubai

## Commercial terms

| Field | Value | Origin |
|---|---|---|
| Units | 160 | DLD registry |
| Declared handover | Q1 2025 | Developer supplied |
| Payment plan | 60/40 | Developer supplied |
| Down payment | 5% | Developer supplied |

## Dubai Land Department register

| Field | Value | Origin |
|---|---|---|
| DLD project number | 1895 | DLD registry |
| Construction | 100% | DLD registry |
| DLD inspection date | 2025-02-12 | DLD registry |
| Registry status | Ready | DLD registry |
| Escrow bank | Dubai Islamic Bank | DLD registry |

### DLD inspection history

| Date | Completion |
|---|---|
| 2018-02-28 | 0.1% |
| 2018-06-12 | 4.6% |
| 2020-06-04 | 4.6% |
| 2023-09-04 | 6.69% |
| 2024-04-24 | 40.74% |
| 2024-09-13 | 58.29% |
| 2025-02-12 | 100% |

> Completion is recorded at a DLD technical inspection. An unchanged value between two dates means no new inspection, not a stopped site. The declared handover is the date held in the register or stated by the developer, not the actual completion.

## Sources and provenance

- DLD registry — taken from the Dubai Land Department register as recorded.
- Developer supplied — stated by the developer; prices change without notice.
- Our calculation — computed by us from the first two.

## Links

- Project page: https://continentalclub.ae/project/island-park-i-dubai-creek-harbour/
- The same record as JSON: https://continentalclub.ae/project/island-park-i-dubai-creek-harbour.json
- Methodology and origin labels: https://continentalclub.ae/methodology/#provenance
- RU: https://continentalclub.ae/ru/project/island-park-i-dubai-creek-harbour-ru/

Record updated: 2026-10-08

---

How to cite: "Island Park I — Continental Club Property, from Dubai Land Department registry and developer data, 2026-10-08, https://continentalclub.ae/project/island-park-i-dubai-creek-harbour/"