# Creek Horizon

Emaar Properties · Dubai Creek Harbour · Dubai

## Commercial terms

| Field | Value | Origin |
|---|---|---|
| Units | 559 | DLD registry |
| Declared handover | Q3 2020 | Developer supplied |

## Dubai Land Department register

| Field | Value | Origin |
|---|---|---|
| DLD project number | 1772 | DLD registry |
| Construction | 100% | DLD registry |
| DLD inspection date | 2021-01-27 | DLD registry |
| Registry status | Ready | DLD registry |
| Escrow bank | Commercial Bank of Dubai | DLD registry |

### DLD inspection history

| Date | Completion |
|---|---|
| 2017-05-21 | 6.45% |
| 2017-09-25 | 7.75% |
| 2018-01-15 | 11.59% |
| 2018-05-02 | 16.92% |
| 2018-08-29 | 20.91% |
| 2018-12-31 | 30.91% |
| 2019-03-24 | 41.56% |
| 2019-07-28 | 55.33% |
| 2019-09-12 | 65.66% |
| 2020-01-05 | 80.64% |
| 2020-04-20 | 91.26% |
| 2020-07-27 | 95.04% |
| 2020-11-17 | 98.22% |
| 2021-01-27 | 100% |

> Completion is recorded at a DLD technical inspection. An unchanged value between two dates means no new inspection, not a stopped site. The declared handover is the date held in the register or stated by the developer, not the actual completion.

## Sources and provenance

- DLD registry — taken from the Dubai Land Department register as recorded.
- Developer supplied — stated by the developer; prices change without notice.
- Our calculation — computed by us from the first two.

## Links

- Project page: https://continentalclub.ae/project/creek-horizon-dubai-creek-harbour/
- The same record as JSON: https://continentalclub.ae/project/creek-horizon-dubai-creek-harbour.json
- Methodology and origin labels: https://continentalclub.ae/methodology/#provenance
- RU: https://continentalclub.ae/ru/project/creek-horizon-dubai-creek-harbour-ru/

Record updated: 2026-10-12

---

How to cite: "Creek Horizon — Continental Club Property, from Dubai Land Department registry and developer data, 2026-10-12, https://continentalclub.ae/project/creek-horizon-dubai-creek-harbour/"