# Altus

Emaar Properties · Dubai Creek Harbour · Dubai

## Commercial terms

| Field | Value | Origin |
|---|---|---|
| Units | 283 | DLD registry |
| Declared handover | Q1 2029 | Developer supplied |

## Dubai Land Department register

| Field | Value | Origin |
|---|---|---|
| DLD project number | 3184 | DLD registry |
| Construction | 64.2% | DLD registry |
| DLD inspection date | 2026-06-25 | DLD registry |
| Registry status | Active | DLD registry |
| Escrow bank | Mashreq Bank | DLD registry |

### DLD inspection history

| Date | Completion |
|---|---|
| 2024-08-02 | 0% |
| 2025-05-23 | 9.9% |
| 2025-10-21 | 24.27% |
| 2025-12-04 | 31.1% |
| 2026-03-17 | 51.65% |
| 2026-06-25 | 64.2% |

Pace (Our calculation): 4.92% per month across inspections from 2025-10-21 to 2026-06-25; at this rate 100% falls on 2027-02-01. An estimate, not a developer commitment.

> Completion is recorded at a DLD technical inspection. An unchanged value between two dates means no new inspection, not a stopped site. The declared handover is the date held in the register or stated by the developer, not the actual completion.

## Sources and provenance

- DLD registry — taken from the Dubai Land Department register as recorded.
- Developer supplied — stated by the developer; prices change without notice.
- Our calculation — computed by us from the first two.

## Links

- Project page: https://continentalclub.ae/project/altus-dubai-creek-harbour/
- The same record as JSON: https://continentalclub.ae/project/altus-dubai-creek-harbour.json
- Methodology and origin labels: https://continentalclub.ae/methodology/#provenance
- RU: https://continentalclub.ae/ru/project/altus-dubai-creek-harbour-ru/

Record updated: 2026-10-08

---

How to cite: "Altus — Continental Club Property, from Dubai Land Department registry and developer data, 2026-10-08, https://continentalclub.ae/project/altus-dubai-creek-harbour/"